QDA OWN SCHEMES

TIMELINE FOR QDA OWN HOUSING SCHEMES

 
PROCEDURES & DOCUMENTS FOR ISSUANCE OF VARIOUS APPROVALS for INDIVIDUAL PLOT

1.    PROCEDURE FOR GRANT OF N.O.C (Res: or Comm:) FOR INDIVIDUAL PLOT                                                     

       BY ESTATE DIRECTORATE, QDA.

 Procedure

  1. Submission of application along with documents to Estate Directorate, QDA.
  2. Application by the owner of plot for NOC to Director Estate after submission of all dues
  3. CNIC of owner of the plot
  4. Original Allotment Order
  5. Payment / Installment Book

 

  1. Scrutiny of documents by the Estate Directorate
  2. If any observation found, allottee will be informed accordingly

If no observation found, Preparation and issuance of N.O.C by the Estate Directorate, QDA.

 

1.     DOCUMENTS REQUIRED FOR ISSUANCE OF N.O.C ( Res: or Comm:) FOR INDIVIDUAL PLOT

        BY THE ESTATE DIRECTORATE, QDA.

 

S.#    DocumentsOriginalP/CopiesAttestationAmount
1ApplicationYesNo  
2CNIC of Owner of  plotNoYes  
3Allotment Order of the plotYesNo  
4Payment / Installment BookYesNo  

 

 

 

2.     PROCEDURE FOR GRANT OF SITE PLAN FOR INDIVIDUAL PLOT BY

        BUILDING CONTROL SECTION, QDA

          View Site Plan Document

  1. Submission of application along with documents to Building Control desk.
  2. Application by the owner for Site Plan to Chief Architect
  3. CNIC of owner of the plot
  4. No Objection Certificate issued by Estate Directorate

 

  1. Scrutiny of documents by Building Control Section
  2. If any observation found, allottee will be informed accordingly

If no observation found, Preparation and issuance of Site Plan by Building Control Section, QDA.

 

2.      DOCUMENTS REQUIRED FOR ISSUANCE OF SITE PLAN FOR INDIVIDUAL PLOT

         BY BUILDING CONTROL SECTION, QDA.

S.#DocumentsOriginalP/CopiesAttestationAmount
1ApplicationYesNo  
2CNIC of the Owner of  plotNoYes  
3No Objection Certificate issued

 

by Estate Directorate.

YesNo  

 

3.     PROCEDURE FOR GRANT OF BUILDING PERMIT FOR INDIVIDUAL PLOT

        BY BUILDING CONTROL SECTION, QDA

 

  1. Submission of application along with documents to Building Control desk.
  2. No Objection Certificate issued by Estate Directorate
  3. Site Plan issued by Building Control Section QDA
  4. Submission of detailed Drawings / Plans signed & stamped by an Architect duly Registered with Pakistan Council of Architects & Town Planners (PCATP )
  5. CNIC of owner of the plot

 

  1. Scrutiny of documents by Building Control Section
  2. If any observation found, allottee will be informed accordingly

iii.        If no observation found, allottee will submit the layout plan prepared by an Architect

  1. Scrutiny of Building Design as per QDA Building Rules
  2. Map, Security and possession Fee (designated bank, NBP)

vi.        Issuance of Building Permit & Possession of plot by Chief Architect, QDA.

 

3.     DOCUMENTS REQUIRED FOR ISSUANCE OF BUILDING PERMIT FOR INDIVIDUAL PLOT

        BY BUILDING CONTROL SECTION, QDA.

 

S.#DocumentsOriginalP/CopiesAttestationAmount
1ApplicationYesNo  
2CNIC of Owner of  plotNoYes  
3Site Plan of the plot issued by the Building Control Section, QDAYesNo  
4Map, Security and possession Fee (designated bank, NBP)    

QDA Private SCHEMES

TIMELINE FOR PRIVATE HOUSING SCHEMES

 TIMELINE FOR PRIVATE HOUSING SCHEME

TIME LINE FOR PROCESSING OF APPLICATION FOR GRANT OF PLANNING

PERMISSION TO PRIVATE HOUSING SCHEMES

S.No

TASK

OFFICER / OFFICIAL

No. OF DAYS

1

Submission of Application along with required documents and depositing Planning Permission Fee

D.D T.P

2

2

Scrutiny & further processing

D.D T.P

3

3

Forwarded to DG QDA for perusal

Dir T.P

1

4

Letter to the sponsor for Provision of “Certificates” for Planning Permission.

Dir T.P

2

5

Submission of “Certificates” by the sponsor

D.D. T.P

15

6

Scrutiny of the Certificates

D.D. T.P

5

7

If any observation found, letter will be addressed to the Owner / Sponsor

D.D. T.P

1

8

If no observation found, the case will be placed before the Private Housing Committee for consideration and visit of the site

Dir T.P

3

9

Minutes of the Committee meeting will be issued for approval of DG, QDA.

Chairman / Chief Engineer

2

10

Advertisement will be made in the newspaper

Dir  T.P

7

11

If no observation arises, Planning Permission will be issued

Dir  T.P

2

 

TOTAL TIME LINE

 

43

TIMELINE FOR TECHNICAL CLEARANCE AND APPROVAL

OF PLAN OF THE SCHEME.

S.No

TASK

OFFICER / OFFICIAL

No. OF DAYS

1

Provision of Drawings / Documents and depositing Technical Scrutiny Fee

Dir T.P

2

2

Scrutiny of drawings will be made as per QDA Town Planning Rules

A.D T.P-I

3

3

If any observation found, letter will be addressed to the Owner / Sponsor

D.D  T.P

2

4

Press-Release in Daily Newspapers

Dir T.P

3

5

Issuance of final N.O.C & approval of Layout Plan

Dir T.P

2

 

TOTAL TIME LINE

 

12

TIMELINE FOR EXECUTION OF AGREEMENTS AND DEVELOPMENT ACTIVITIES / PERMIT

S.No

TASK

OFFICER / OFFICIAL

No. OF DAYS

1

Provision of Stamp Duties by the sponsor

D.D T.P

3

2

Preparation of Agreement

Dir T.P

2

3

Execution of the Mortgage Deed

D.G  QDA

5

4

Scrutiny of Services Drawings (Roads, Sewerage, Water supply, Gasification, Electrification etc)

Dir: Works-I

A.E-Roads

A.E Sewerage

5

5

If any observation found, letter will be addressed to the Owner / Sponsor

Dir Works-I

1

6

Submitted to DG QDA for approval of Development Activities in the Scheme.

Dir Works-I

2

7

Issuance of Development Permit

Dir Works-I

1

8

Monitoring & Evaluation

Chief Engineer

 
 

TOTAL TIME LINE

 

19

PROCEDURE FOR GRANT OF PLANNING PERMISSION

AND N.O.C TO PRIVATE HOUSING SCHEMES.                                                                                                                                                              

  1. Submission of application along with ownership documents on T.P Reception desk
  2. Mutation of land
  3. CNIC of Sponsor / Developer
  4. Aks e Shjara
  5. Location Plan
  6. Land use Certificate
  7. Non encumbrance certificate
  8. Water availability certificat
  9. Scrutiny of Documents by T.P Section and for Approval of DG QDA.
  10. After approval of application, letter will be issued for submission of “Certificates”.

 

  1. Provision of Certificates for obtaining Planning Permission
  2. Registration certificate of FBR and BRA (Balochistan Revenue Authority)
  3. Certificate for availability of Electricity (QESCO)
  4. Certificate for availability of Gas (SSGC)
  5. Certificate for availability of Sewerage and sanitation (WASA)
  6. Certificate for availability of Telephone/ DSL net (PTCL)
  7. Environmental approval/clearance certificate (EPA)
  8. Registration certificate from Social Welfare / Industries Deptt.
  9. Planning Permission Fee (designated bank, NBP)

 

  1. Scrutiny of above certificates / documents
  2. If any observation found, letter will be addressed to the Owner
  • If no observation found, the case will be placed before the Private Housing Committee for consideration and visit of the site.

             Private Housing Committee consists of the following:

             Chief Engineer, QDA                         Chairman

             Director Works, QDA                         Member

              Director Town Planning             Member / Secretary

  1. Minutes of the Committee meeting will be issued
  2. If any observation found, letter will be addressed to the Owner
  3. If no observation found, Director T.P will submit the case for approval to DG QDA.
  • After approval of DG QDA, advertisement will be made in the newspaper regarding any objection by general public. (Advertisement charges will be paid by the owner of the scheme).
  • After seven days from the date of advertisement in the newspaper, Planning permission will be granted to the owner of the scheme by Director Town Planning, QDA.

 

  1. Provision of Documents / Drawings for obtaining N.O.C of the scheme
  2. Survey plan, 4 sets ammonia print
  3. Layout plan, 4 sets ammonia print
  4. Location plan, 4 sets ammonia print
  5. General irrevocable Power of Attorney (duly Registered with Sub Registrar Quetta) if land is not mutated in the name of sponsor / developer
  6. Scrutiny Fee (designated bank, NBP)

 

  1. Scrutiny of above drawings will be made as per QDA T.P Rules
  2. If any observation found, letter will be addressed to the Owner
  • If no observation found, the case will be submitted to DG QDA for approval of NOC
  1. QDA will publish a Press-Release in Daily Newspapers regarding issuance of NOC of the scheme.
  2. Mortgage Deed / Agreement
  3. QDA will mortgage 30% of the salable residential plots to ensure the development activities as per approved layout plan and to secure the public interest.
  4. QDA will publish as advertisement in the Daily Newspapers regarding 30% mortgaged salable residential plots, clearing mentioning Block Nos, Plot Nos, and area of the plot etc.
  5. Mortgage Deed / Agreement will be executed on a stamp paper

 

  1. Development Activities Permit
  2. On provision of all the services drawings i.e Water supply, Electrification, Gasification, Sewerage etc., the Engineering Wing QDA will scrutinize the services drawings.
  3. If any observation found, letter will be addressed to the Owner
  4. If no observation found, the case will be submitted to DG QDA for approval of Development activities in the scheme.