TIMELINES FOR BUILDING PERMIT/CONSTRUCTION

TIMELINE FOR SUBMISSION OF APPLICATION ALONG WITH DOCUMENTS TO BUILDING

CONTROL DESK FOR ISSUANCE OF BUILDING PERMIT / CONSTRUCTION.

S.No TASK OFFICER / OFFICIAL No. OF DAYS
1 Obtaining No Objection Certificate Director Estate Commercial OR Residential 5
2 Issuance of Site Plan Director Building Control 5
3 Submission of Drawings as per QDA Building Rules by the alottee Director Building Control 1
4 Scrutiny of submission Drawings A.D Building Control 4
5 If any observation found, allottee will be informed accordingly A.D Building Control 1
6 If no observation found, Building Permit will be issued Director Building Control 3
7 Preparation of  Challan Fee for Map, Security and Possession (designated Bank, NBP) A.D Building Control 1
8 Possession of plot Building Surveyor 2
TOTAL TIME LINE 22