TIMELINE FOR QDA OWN HOUSING SCHEMES

PROCEDURES & DOCUMENTS FOR ISSUANCE OF VARIOUS APPROVALS for INDIVIDUAL PLOT

1.    PROCEDURE FOR GRANT OF N.O.C (Res: or Comm:) FOR INDIVIDUAL PLOT                                                     

       BY ESTATE DIRECTORATE, QDA.

 Procedure

  1. Submission of application along with documents to Estate Directorate, QDA.
  2. Application by the owner of plot for NOC to Director Estate after submission of all dues
  3. CNIC of owner of the plot
  4. Original Allotment Order
  5. Payment / Installment Book

 

  1. Scrutiny of documents by the Estate Directorate
  2. If any observation found, allottee will be informed accordingly

If no observation found, Preparation and issuance of N.O.C by the Estate Directorate, QDA.

 

1.     DOCUMENTS REQUIRED FOR ISSUANCE OF N.O.C ( Res: or Comm:) FOR INDIVIDUAL PLOT

        BY THE ESTATE DIRECTORATE, QDA.

 

S.#     Documents Original P/Copies Attestation Amount
1 Application Yes No    
2 CNIC of Owner of  plot No Yes    
3 Allotment Order of the plot Yes No    
4 Payment / Installment Book Yes No    

 

 

 

2.     PROCEDURE FOR GRANT OF SITE PLAN FOR INDIVIDUAL PLOT BY

        BUILDING CONTROL SECTION, QDA

          View Site Plan Document

  1. Submission of application along with documents to Building Control desk.
  2. Application by the owner for Site Plan to Chief Architect
  3. CNIC of owner of the plot
  4. No Objection Certificate issued by Estate Directorate

 

  1. Scrutiny of documents by Building Control Section
  2. If any observation found, allottee will be informed accordingly

If no observation found, Preparation and issuance of Site Plan by Building Control Section, QDA.

 

2.      DOCUMENTS REQUIRED FOR ISSUANCE OF SITE PLAN FOR INDIVIDUAL PLOT

         BY BUILDING CONTROL SECTION, QDA.

S.# Documents Original P/Copies Attestation Amount
1 Application Yes No    
2 CNIC of the Owner of  plot No Yes    
3 No Objection Certificate issued

by Estate Directorate.

Yes No    

 

3.     PROCEDURE FOR GRANT OF BUILDING PERMIT FOR INDIVIDUAL PLOT

        BY BUILDING CONTROL SECTION, QDA

 

  1. Submission of application along with documents to Building Control desk.
  2. No Objection Certificate issued by Estate Directorate
  3. Site Plan issued by Building Control Section QDA
  4. Submission of detailed Drawings / Plans signed & stamped by an Architect duly Registered with Pakistan Council of Architects & Town Planners (PCATP )
  5. CNIC of owner of the plot

 

  1. Scrutiny of documents by Building Control Section
  2. If any observation found, allottee will be informed accordingly

iii.        If no observation found, allottee will submit the layout plan prepared by an Architect

  1. Scrutiny of Building Design as per QDA Building Rules
  2. Map, Security and possession Fee (designated bank, NBP)

vi.        Issuance of Building Permit & Possession of plot by Chief Architect, QDA.

 

3.     DOCUMENTS REQUIRED FOR ISSUANCE OF BUILDING PERMIT FOR INDIVIDUAL PLOT

        BY BUILDING CONTROL SECTION, QDA.

 

S.# Documents Original P/Copies Attestation Amount
1 Application Yes No    
2 CNIC of Owner of  plot No Yes    
3 Site Plan of the plot issued by the Building Control Section, QDA Yes No    
4 Map, Security and possession Fee (designated bank, NBP)        