Registration certificate from Social Welfare / Industries Deptt.
Planning Permission Fee (designated bank, NBP)
Scrutiny of above certificates / documents
If any observation found, letter will be addressed to the Owner
If no observation found, the case will be placed before the Private Housing Committee for consideration and visit of the site.
Private Housing Committee consists of the following:
Chief Engineer, QDA Chairman
Director Works, QDA Member
Director Town Planning Member / Secretary
Minutes of the Committee meeting will be issued
If any observation found, letter will be addressed to the Owner
If no observation found, Director T.P will submit the case for approval to DG QDA.
After approval of DG QDA, advertisement will be made in the newspaper regarding any objection by general public. (Advertisement charges will be paid by the owner of the scheme).
After seven days from the date of advertisement in the newspaper, Planning permission will be granted to the owner of the scheme by Director Town Planning, QDA.
Provision of Documents / Drawings for obtaining N.O.C of the scheme
Survey plan, 4 sets ammonia print
Layout plan, 4 sets ammonia print
Location plan, 4 sets ammonia print
General irrevocable Power of Attorney (duly Regustered with Sub Registrar Quetta) if land is not mutated in the name of sponsor / developer
Scrutiny Fee (designated bank, NBP)
Scrutiny of above drawings will be made as per QDA T.P Rules
If any observation found, letter will be addressed to the Owner
If no observation found, the case will be submitted to DG QDA for approval of NOC
QDA will publish a Press-Release in Daily Newspapers regarding issuance of NOC of the scheme.
Mortgage Deed / Agreement
QDA will mortgage 30% of the salable residential plots to ensure the development activities as per approved layout plan and to secure the public interest.
QDA will publish as advertisement in the Daily Newspapers regarding 30% mortgaged salable residential plots, clearing mentioning Block Nos, Plot Nos, and area of the plot etc.
Mortgage Deed / Agreement will be executed on a stamp paper
Development Activities Permit
On provision of all the services drawings i.e Water supply, Electrification, Gasification, Sewerage etc., the Engineering Wing QDA will scrutinize the services drawings.
If any observation found, letter will be addressed to the Owner
If no observation found, the case will be submitted to DG QDA for approval of Development activities in the scheme.